The crane is booked. Nobody wants to own the delay.
The turbine supplier has reserved its installation crew and crane for a narrow working window. A delay in the civil works means the access route and crane pad will not be ready as expected. The site team assumes the supplier can rearrange; the supplier expects the site team to protect the agreed slot. Nobody wants to be first to confirm a delay with costly consequences. Updates remain cautiously optimistic while alternative arrangements go undiscussed. By the time the position is clear, flexibility has been lost and the groups are arguing about who carries the cost.